APS Beamline Commissioning Activity Approval Form


Sequence No : 01-BM-04-16
Sector : 01 Beamline : BM
Start Date : 07/20/2004 Duration : 1 day
Date and Time of Submission : 07-19-04 13:03

Commissioning Envelope :
The maximum operating current is 100ma ma
Modes : Operation with normal operating conditions

Activity Description:
Participate in 1296 bunch studies.

Commissioning Team Members

First and Last Name AffiliationPhone Number
1. Jin Wang XOR-CAT 2-9125

Special Safety Concerns:

Submitted by Commissioning Activity Team Leader:
Name : R. Monroe Date : 07-19-04
E-Mail : monroe@aps.anl.gov

ADD for Operations Comment :
No additional restrictions required. Study begins 9am and extends to 5pm.
Approved by ADD for Ops./Designee : Klaffky on 07-19-04